Task H has duration of 6

Task H has duration of 6

Task H has duration of 6 days, an ES (earliest start) of 25 days, an EF (earliest finish) of 30 days, a LS (latest start) of 25 days, and a LF (latest finish) of 30 days. There are ________ days of total slack for task HA. 0 daysB. 1 dayC. 5 daysD. 6 days